The Decorah City Council Monday night approved the low bid on the Quarry Street storm sewer Improvements project.
The work is being done as a companion project to the work being done later this year on Locust Road.
The City Engineer estimated the cost of the project as $526,072.25. The city received two bids, both lower than the estimate. Skyline Construction has a bid of $437,717.50, while JB Holland made a bid of $484,271.45.
City council members Monday night approved the low bid from Skyline Construction.