Work is moving along well on new Toppling Goliath brewery

Posted: Sun, Apr 16, 2017 8:24 PM
Work continues inside the 52,000 square foot building

Toppling Goliath officials are still expecting their new brewery in Decorah will open some time this fall.

decorahnews.com toured the 52,000 square foot facility late last week.  It's obvious the new facility will allow a huge jump in production for the company.

There's 26,000 square feet of space for brewing beer inside the complex and another 11,000 square feet for warehousing and distribution.

But for the public, the most visible space in the brewery will be the sampling room.  That room will have 8,500 square feet of space on the ground floor.  But a balcony has been added to the plans.  That will add another 4,500 square feet of space.  Toppling Goliath officials say the room will hold up to 750 people at one time.

The new brewery is being built on Prosperity Road in the Decorah Business Park, near the Decorah Airport. 

A view of the sampling room
A special VIP area will be in the sampling room
Offices at the new brewery will be much bigger than at the current facility off Old Stage Road
Toppling Goliath has created its own water filtration facility--to make sure the water for its beer is just right