City of Decorah wraps up Claiborne Drive/State Street project

Posted: Mon, Oct 21, 2013 9:02 PM

The City of Decorah has approved the final payments on work on the Claiborne Drive and State Street intersection project.

The work wound up costing $352,000, with the Decorah School District paying 10 percent of the cost.  The project used more rock base than was expected--around $15,000 worth.  But savings in other areas kept the overall increase in the cost of the project to $10,038.89.

The Decorah City Council on Monday night approved the final payment for the project.