The contractor on the Trout Run Trail Bridge over Highway 9 will be setting I-beam "falsework" over eastbound lanes on Tuesday (April 3rd) and another section of "falsework" over westbound lanes on Friday (April 6th).
This is an important part of the overall project as it constructs the frame and form work for the bridge. Once this framing is in place there will be a 14 foot, 3 inch vertical restriction on each lane. Crews will continue to construct wood forms to create the shape of the bridge over the next few weeks.
Lane width restrictions are still in effect as previously noted.